A and B can together complete a task in 21 days. If A alone takes 42 days to complete the task, then the number of days that B would take to do the task alone is: |
32 36 42 27 |
42 |
A + B = 21 days, A = 42 days, ⇒ Efficiency of A + B = 2, ⇒ 1 + B = 2 ⇒ B = 1, ⇒ Time required by B to complete the work alone = \(\frac{42}{1}\) = 42 days, ..(\(\frac{Work}{Efficiency}\) = Time) |