P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two third part of same work? |
12 15 18 21 |
12 |
P + Q = 12 days, P = 36 days, ⇒ Simplifying, we can get that Q = 2 (Efficiency) ⇒ \(\frac{2}{3}\) of total work = \(\frac{2}{3}\) x 36 = 24 units. ⇒ Time required for Q alone to complete 24 units = \(\frac{24}{2}\) = 12 days. ..(\(\frac{Work}{Efficiency}\) = Time)
|