Read the following passage and answer the question.
A company manufactures radios and supplies them to dealers all over the country. Its production target was 5,000 radios per week. The manager decided that a deviation in production of up to 100 units would be acceptable. At the end of the first week, production was 4,500 radios. The next week, production increased to 4,700 radios. A week later, only 4,600 radios were produced. On investigation, it was found that the fluctuation in production was due to irregular electricity supply.
Suppose the deviation caused by the irregular electricity supply cannot be removed by any managerial action. What may the company have to do?
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → Revise the production standard of 5,000 radios per week
| Option | Reason |
|---|---|
| Option (1) Allow overtime work on the days when the power supply is regular. Incorrect. | Permission for overtime is a corrective action taken by managers; here no managerial action can remove the deviation, so overtime cannot correct it. |
| Option (2) Assign additional workers to the shifts that have power supply. Incorrect. | Assigning additional workers is also a managerial corrective action; the case says no managerial action can remove this deviation, so extra workers cannot correct it. |
| Option (3) Revise the production standard of 5,000 radios per week. Correct. | When a deviation cannot be corrected through managerial action, the standards may have to be revised; so the company must revise its target of 5,000 radios a week. |
| Option (4) Train the employees to make up the output lost in power cuts. Incorrect. | Training of employees is a managerial corrective action for a missed target; the case rules out every managerial action, so training cannot remove this deviation. |
NCERT Extract (2026-27 Edition): Correct option (3) Step 5: Taking Corrective Action: “In case the deviation cannot be corrected through managerial action, the standards may have to be revised.” Wrong options (1), (2) and (4) Step 5: Taking Corrective Action: “Corrective action might involve training of employees if the production target could not be met. Similarly, if an important project is running behind schedule, corrective action might involve assigning of additional workers and equipment to the project and permission for overtime work.” |