If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day? |
16 10 12 15 |
10 |
Formula to be used here, M1 x D1 x H1 = M2 x D2 x H2 ⇒ where, M = No. of men, D = no of days, H = No. of Hours, ⇒ Putting in the values, ⇒ 10 x 12 x 7 = 14 x D2 x 6 ⇒ D2 = 10 days. |