A can do a piece of work in 36 days and B in 54 days. How many days will both take together to complete the work? |
17 20 18 16 |
18 |
Total work = L.C.M. of time taken by individual workers Efficiency = \(\frac{Total\; work}{No.\; of\; days}\) Therefore, A : B No. of days 36 : 54 → L.C.M. = 90 Efficiency 2 : 3 Total= 5 When they work together, efficiency = 5 Say, total work = 90 Thus, No. of days = \(\frac{90}{5}\) = 18 |