12 men can do a work in 8 days while 4 boys can do it in 40 days. In how many days 9 boys and 3 men together will complete the same work ? |
10 days 280/13 days 80/7 days 260/17 days |
80/7 days |
Given, 12 Men x 8 days = 4 Boys x 40 days, ..(1) ⇒ 3 Men = 5 Boys ⇒ Men : Boys = 5 : 3 (Efficiency) Putting Efficiency in (1), ⇒ 12 (5) x 8 = 480 units. ..(Efficiency × Days = Total work) ⇒ Total efficiency of 9 Boys and 3 Men = 9(3) + 3(5) = 27 +15 =42 ⇒ Time required for 9 Boys and 3 Men to complete total work = \(\frac{480}{42}\) = \(\frac{80}{7}\) days. |