Question:

25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task?

Options:

12 days

10 days

15 days

18 days

Correct Answer:

10 days

Explanation:

Formula to be used here,

\( { M}_{1 } \) x \( { D}_{1 } \)  = \( { M}_{2 } \) x \( { D}_{2 } \)

⇒ where, M = No. of Men, D = No. of Days,

⇒ Putting values in the formula,

⇒ 25 x 12 = 30 x \( { D}_{2 } \)

\( { D}_{2 } \) = 10 days.