A takes twice as much time as B and thrice as much time as C to finalise a task. Working together, they can complete the task in 8 days. The time (in days) taken by A, B and C, respectively, to complete the task is: |
42, 21, 14 60, 30, 20 54, 27, 18 48, 24, 16 |
48, 24, 16 |
Efficiency ∝ \(\frac{1}{time}\) A : B : C Time 3 : : 1 2 : 1 ______________ Time 6 : 3 : 2 Efficiency 1 : 2 : 3 Adding efficiency 1 + 2 + 3 = 6 work = efficiency x time taken = 8 x 6 = 48 units So, A finalizes the work in = 6 x 8 = 48 days So, B finalizes the work in = 3 x 8 = 24 days So, C finalizes the work in = 2 x 8 = 16 days Therefore time taken by A, B and C, respectively, to complete the task is: 48, 24, 16. |