30 men can complete a piece of work in 24 days. 12 days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work? |
12 days 8 days 10 days 9 days |
9 days |
Formula to be used here, \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2 } \) where, M = No. of Men, D = No. of Days, ⇒ Putting in the formula, ⇒ 30 x 12 = 40 x \( { D}_{2 } \) ⇒ \( { D}_{2 } \) = 9 days, |