Practicing Success
Raju, Shobh and Mohan can do a work in 15 days, 20 days and 25 days respectively. In how many days, will the work be finished, if they do it on alternate days? |
$15 \frac{9}{10}$ days $18 \frac{7}{10}$ days $21 \frac{7}{10}$ days $18 \frac{9}{10}$ days |
$18 \frac{9}{10}$ days |
If A, B, C start working on alternate days by considering them as a single block of eff = 47 in 6 x 3 days, work done = efficiency x no. of days = 47 x 6 = 282 Remaining work = 300 - 282 = 18 This will take A = \(\frac{18}{20}\) = \(\frac{9}{10}\) days Total time taken to finish the complete work = 18\(\frac{9}{10}\) days |