Arrange the steps of the controlling process in a logical sequence.
(A) Corrective action might involve training of employees if the production target could not be met.
(B) Setting standards of performance
(C) Performance of a worker in terms of units produced is measured against the standard output.
(D) Critical point control and management by exception should be used in case of deviations.
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 4
The correct answer is Option (4) → (B), (C), (D), (A)
The five steps of controlling are: setting performance standards, measuring actual performance, comparing it with the standards, analysing deviations and taking corrective action.
Step 1 — (B) Setting standards of performance: first the manager decides what results are expected.
Step 2 — (C) Performance measured against the standard output: this covers measuring and comparing. The units a worker produces are measured and compared with the standard. This shows the gap between actual and expected results.
Step 3 — (D) Critical point control and management by exception: the gap (deviation) is analysed. The manager decides which deviations are small and acceptable and which are serious. He pays attention to the key areas and to the big deviations only.
Step 4 — (A) Corrective action: the problem is put right. For example, workers are trained if the production target was not met.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. Comparison becomes easier when standards are set in quantitative terms. For instance, performance of a worker in terms of units produced in a week can be easily measured against the standard output for the week.” “Step 4: Analysing Deviations: Some deviation in performance can be expected in all activities. It is, therefore, important to determine the acceptable range of deviations. Also, deviations in key areas of business need to be attended more urgently as compared to deviations in certain insignificant areas. …” “Critical Point Control: It is neither economical nor easy to keep a check on each and every activity in an organisation. Control should, therefore, focus on key result areas (KRAs) which are critical to the success of an organisation. …” “Step 5: Taking Corrective Action: … Corrective action might involve training of employees if the production target could not be met. Similarly, if an important project is running behind schedule, corrective action might involve assigning of additional workers and equipment to the project and permission for overtime work. …” |