A certain number of people were supposed to complete a work in 24 days. They work however took 32 days since 9 people were absent throughout. How many people were supposed to be working originally?
|
20 18 24 36 |
36 |
According to the question, the following equations will be formed: Let original workers be "w" w x 24 = (w - 9) x 32 w x 24 = 32w - 288 32w - 24w = 288 8w = 288 w = 36 workers |