Simran can complete a work in 20 days. How much work will be done by her in 12 days? |
$\frac{3}{5}$ $\frac{5}{8}$ $\frac{4}{5}$ $\frac{2}{3}$ |
$\frac{3}{5}$ |
Simran can complete a work in = 20days so in one day she can complete = 1/20 work and in12 days she can complete = 12/20 = 3/5th part of work |