Which of the following is NOT a step in the controlling process?
Answer & explanation
Correct answer: option 4
The correct answer is Option (4) → Taking follow-up action
Option (1) Setting performance standards — A step in the controlling process. It is the first step. Standards are the benchmarks against which actual performance is measured.
Option (2) Analysing deviations — A step in the controlling process. It is the fourth step. The manager finds which deviations are significant and what caused them.
Option (3) Taking corrective action — A step in the controlling process. It is the fifth and final step, used when deviations go beyond the acceptable range.
Option (4) Taking follow-up action — Not a step in the controlling process. Follow-up action is the last step of the planning process, where managers check that the plan is being put into action. The controlling process ends with taking corrective action.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. …” |