20 workers can paint 24 walls in 36 days. In how many days can 30 workers paint 20 walls? |
20 30 24 15 |
20 |
Formula to be used here, ⇒ \(\frac{M_1\;×\;D_1}{M_2\;×\;D_2}\) = \(\frac{W_1}{W_2}\) where, M = No. of men, D = No. of Days, W = Unit of Work, ⇒ Putting in the values, ⇒ \(\frac{20\;×\;36}{30\;×\;D_2}\) = \(\frac{24}{20}\) ⇒ \( { D}_{2 } \) = 20 days. |