To do a certain work, the ratio of efficiencies of A and B is 13 : 11. Working together, they can complete the same work in 19\(\frac{1}{2}\) days. A alone will complete 75% of the same work in? |
20 days 27 days 15 days 10 days |
27 days |
A : B 13 : 11 Total work = \(\frac{39}{2}\) × 24 = 468 A completed 75% work in = 468 × \(\frac{75}{100}\) × \(\frac{1}{13}\) = 27 days |