Numerical Ability

Topic

Time and Work

Question:

A can complete a work in 8 days and B can complete the same work in 11 days. How long will they take, if both work together?

Options:

$4\frac{12}{17}$

$5\frac{12}{19}$

$4\frac{11}{19}$

$4\frac{12}{19}$

Correct Answer:

$4\frac{12}{19}$

Explanation:

A = 8 days, B = 11 days,

⇒ Time required for A + B to complete the total work = \(\frac{88}{11 + 8}\) = \(\frac{88}{19}\) =\( { 4}_{ 19}^{ 12} \) days.