B would have taken 10 hours more than what A would have taken to complete a task. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task? |
30 15 20 10 |
15 |
let A takes n hours, B will take (n+10) hours to do the same work. together they can complete the same work in 12 hours. In 1 hour, A and B together do \(\frac{1}{n}\) + \(\frac{1}{n + 10}\) = \(\frac{1}{12}\) on solving n = 20. [Note: n = -6 is not possible ] So A does the work in 20 hours and B done in (20+10) = 30 days if B does whole work in 30 days then 50% of work will be done in 15 days.
|