Arrange the following cases in ascending order in terms of number of days to complete the same work. (A) P can do (1/3)rd of the work in 5 days. Choose the correct answer from the options given below: |
(A), (C), (D), (B) (A), (C), (B), (D) (A), (B), (C), (D) (B), (A), (D), (C) |
(A), (C), (D), (B) |
The correct answer is Option (1) → (A), (C), (D), (B) Step 1: Find rate of work for each person (A) P can do 1/3 of the work in 5 days
(B) Q can do 1/6 of the work in 4 days
(C) R can do 25% = 1/4 of work in 4 days
(D) S can do 35% = 35/100 = 7/20 of work in 7 days
Step 2: Arrange in ascending order of total days
Ascending order: A, C, D, B |