Which is the correct sequence of steps in the process of planning?
(A) Developing premises
(B) Implementing the plan
(C) Setting objectives
(D) Identifying alternative courses of action and evaluating them
(E) Selecting an alternative
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → (C), (A), (D), (E), (B)
(C) Setting objectives — Step 1. The first and foremost step is to set objectives for the organisation and for each department.
(A) Developing premises — Step 2. Next, managers make assumptions about the uncertain future on which the plans will be based.
(D) Identifying alternative courses of action and evaluating them — Step 3. Then all possible courses of action are listed, and the pros and cons of each are weighed.
(E) Selecting an alternative — Step 4. Then the best plan is chosen. This is the real point of decision making.
(B) Implementing the plan — Step 5. Last, the plan is put into action.
NCERT (2026-27 Edition): “Planning Process … Objectives may be set for the entire organisation and each department or unit within the organisation.” “…Planning is concerned with the future which is uncertain and every planner is using conjucture about what might happen in future.” “…Once objectives are set, assumptions are made. Then the next step would be to act upon them. Evaluating alternative courses: The next step is to weigh the pros and cons of each alternative.” “…This is the real point of decision making. The best plan has to be adopted and implemented.” “…This is concerned with putting the plan into action. …” |