S1 and S2 can do a piece of work together in 18 days, S2 and S3 can do the same work together in 27 days, while S3 and S1 can do it together in 54 days. In how many days can all 3, working together, do 50% of the work ? |
8 days 6 days 7 days 9 days |
9 days |
S1 + S2 = 18 days, S2 + S3 = 27 days, S3 + S1 = 54 days, ⇒ Adding all the efficiencies, ⇒ 2(S1 + S2 + S3) = 6, ⇒ S1 + S2 + S3 = 3, ⇒ Time required by S1 + S2 + S3 to complete 50% of total work = \(\frac{54/2}{3}\) = \(\frac{27}{3}\) = 9 days, ..(\(\frac{Work}{Efficiency}\) = Time) |