Practicing Success
A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 4 days B had to leave. Then A working with a new worker C completed the remaining work in 3 days. If C works alone, in how many days he can do 40% of the same work? |
9 8$\frac{1}{2}$ 8 10 |
9 |
A = 15 days, B = 10 days, ⇒ A + B worked for 4 days together = (2 + 3) x 4 = 20 units ..(Efficiency × Days = Total work) ⇒ B left and replaced by C, So, A + C completed the remaining work in 3 days. ⇒ Remaining work = 30 -20 = 10 units. ⇒ \(\frac{10}{2 + C}\) = 3 .. (\(\frac{Work}{Efficiency}\) = Time) ⇒ 10 = 6 + 3C ⇒ 3C = 4 ⇒ C = \(\frac{4}{3}\). ⇒ 40% of 30 = 12 units. ⇒ Time taken by C to complete 40% of the total work = $\frac{12}{\frac{4}{3}}$=\(\frac{12 * 3}{4}\)= 9 days. |