Practicing Success
'A' can do a piece of work in 15 days, which 'B' can do in 10 days. 'B' worked at it for 8 days. 'A' can finish the remaining work in |
5 days 3 days 2 days 10 days |
3 days |
Total work = LCM of 15, 10 = 30 Efficiency of A = 30/15 = 2 Efficiency of B = 30/10 = 3 B work in 8 days ⇒ 8 × 3 ⇒ 24 Remaining work = 30 – 24 = 6 A will complete the remaining work = 6/2 = 3 days |