Practicing Success

Target Exam

CUET

Subject

General Test

Chapter

Numerical Ability

Topic

Time and Work

Question:

40 men can complete a work in 15 days. Three days after they started working, 20 more men joined them. In how many days the total work will be completed?

Options:

12

13

11

10

Correct Answer:

11

Explanation:

40 men complete the work in 15 days

In 3 days, $\frac{1}{5}$ of the work is complete 

20 more men join, 

time taken to complete the remaining  work, 

using the following formula 

$\frac{Men\; \times\; Days}{Work}$ = Constant 

$\frac{40\; \times\; 15}{5}$ = $\frac{60\; \times\; days}{4}$

No. of days = 8

Total time taken to complete the work = 8 + 3 = 11 days