Question:

Which of the following is a prerequisite for controlling?

Options:

Planning

Coordination

Innovation

Opportunity

Correct Answer:

Planning

Explanation:

The correct answer is option 1- Planning.

Planning involves setting of goals. The entire managerial process is concerned with accomplishing predetermined goals through planning, organising, staffing, directing and controlling. Planning provides the goals or standards against which actual performance is measured. By comparing actual performance with some standard, managers can know whether they have actually been able to attain the goals. If there is any deviation it can be corrected. Therefore, we can say that planning is a prerequisite for controlling. If there were no goals and standards, then finding deviations which are a part of controlling would not be possible. The nature of corrective action required depends upon the extent of deviations from the standard.