Question:

25 men can finish a piece of work in 20 days working 7 hours per day. In how many days a group of 21 men will finish the work when they are working 5 hours per day if 2 men of the first group are equal to 3 men of the second group ?

Options:

20

30

50

40

Correct Answer:

50

Explanation:

using formula :-

M1 × D1 × H1 × E1   = M2 × D2 × H2  × E2

ratio of efficiency    E1   :   E2

                             3     :     2

25 × 20 × 7 × 3 =   D2  ×  21 × 5 × 2

D2 =50