A, B and C can complete a piece of work in 6, 8 and 15 days. C alone works for 5 days and then quit . After that in how many days work is completed by A alone ? |
4 5 7 9 |
4 |
Total work = Efficiency × Number of days work done by C = 8 × 5 = 40 remaining work = 120 - 40 = 80 so time taken by A to finish the remaining work = \(\frac{80}{20}\) = 4 days |