Question:

A, B and C can do a work in 16 days, while A and B can do the work in 40 days. In how many days can C do the work alone?

Options:

26.67

25

23.33

30

Correct Answer:

26.67

Explanation:

A + B + C = 16 days,

A + B = 40 days,

⇒ A + B + C = 5,  (Efficiency)

⇒ 2 + C = 5,

⇒ C = 3,

⇒ Time required by C to complete the work alone = \(\frac{80}{3}\) = 26.67 days.     ..(\(\frac{Work}{Efficiency}\) = Time)