Arrange the following steps of controlling process in the correct sequence.
A. Measurement of actual performance
B. Setting performance standards
C. Comparison of actual performance with standards
D. Taking corrective action
E. Analysing deviations
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → B, A, C, E, D
Step 1 — (B) Setting performance standards — This is the first step. Standards are the targets against which work will be measured.
Step 2 — (A) Measurement of actual performance — Once standards are set, the actual work done is measured.
Step 3 — (C) Comparison of actual performance with standards — The actual result is put next to the standard. This shows the gap (deviation).
Step 4 — (E) Analysing deviations — The gaps are studied to find their causes.
Step 5 — (D) Taking corrective action — This is the final step. Steps are taken to remove the causes of the gap.
NCERT (2026-27 Edition): “Step 1: Setting Performance Standards: … The first step in the controlling process is setting up of performance standards. Standards are the criteria against which actual performance would be measured. …” “Step 2: Measurement of Actual Performance: … Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. …” “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. …” “Step 4: Analysing Deviations: … After identifying the deviations that demand managerial attention, these deviations need to be analysed for their causes. Deviations may have multiple causes for their origin. …” “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. …” |