If P works alone, he would take 5 days more to complete the work than if P & Q worked together, if Q worked alone, he would take 20 days more to complete the job than P and Q work together. How many days would they take to complete the work if both of them worked together? |
15 days 10 days 4 days 7 days |
10 days |
Time taken by (X + Y) = P = \(\sqrt {5 × 20}\) = 10 days
Or Let P & Q will finish the work in d days Hence P will take = (d + 5) days Q will take = (d + 20) days \(\frac{1}{(d + 5)}\) + \(\frac{1}{(d + 20)}\) = \(\frac{1}{d}\) \(\frac{d + 20 + d + 5}{(d+ 5) (d + 20)}\) = \(\frac{1}{d}\) 2d2 + 25d = d2 + 25d + 100 d2 = 100 d = 10 days |