A car manufacturing plant produces Sedans and SUV's, using limited resources of steel, labour hours, and machine hours.
- Each Sedan requires 6 tons of steel, 10 labour hours and 8 machine hours.
- Each SUV requires 9 tons of steel, 15 labour hours and 12 machine hours.
- Plant has 600 tons of steel, 1200 labour hours and 1000 machine hours.
- Profit per Sedan is Rs. 50,000 and per SUV is Rs. 80,000
Using any method, obtain an optimal $(x,y)$.
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → $(0,66)$