Read the passage and answer the following questions:
XYZ Logistics faced challenges in meeting delivery deadlines, leading to customer complaints. The management decided to implement a structured control process to ensure timely deliveries.
The company set a standard of delivering 95% of orders within the promised timeframe. A tracking system was introduced to monitor real-time delivery progress, ensuring accurate data collection. Monthly reports revealed that only 85% of orders were delivered on time, falling short of the 95% benchmark. Analysis showed delays occurred due to inefficient route planning and uncoordinated warehouse operations.
To address these issues, XYZ Logistics optimized route planning using AI-based software and trained warehouse staff to streamline operations.
After implementing changes, performance improved to 92% within the first month and met the 95% target in three months. Management regularly reviewed the system to maintain performance.
By implementing all elements of the controlling process, XYZ Logistics ensured continuous improvement and customer satisfaction.
What caused the delivery delays?
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Inefficient route planning and uncoordinated warehouse operations.
Option (1) High fuel costs — Incorrect. The passage does not mention fuel costs.
Option (2) Inefficient route planning and uncoordinated warehouse operations. — Correct. The passage says: “Analysis showed delays occurred due to inefficient route planning and uncoordinated warehouse operations.” Finding the cause of a deviation is the fourth step of controlling. Without it, the manager cannot choose the right corrective action. Both steps it took (AI-based route planning and staff training) were aimed at them.
Option (3) Lack of vehicles — Incorrect. The passage does not say the company had too few vehicles.
Option (4) Poor marketing — Incorrect. The problem was late delivery, not a lack of customers.
NCERT (2026-27 Edition): “Step 4: Analysing Deviations: … After identifying the deviations that demand managerial attention, these deviations need to be analysed for their causes. Deviations may have multiple causes for their origin. …” “…It is necessary to identify the exact cause(s) of deviations, failing which, an appropriate corrective action might not be possible. The deviations and their causes are then reported and corrective action taken at appropriate level.” |