A work can be completed by X men in 15 days. 10 more men join them after 3 days. The remaining work is now completed in 8 days. What is the value of X? |
16 20 12 24 |
20 |
Formula to be used here, \( { M}_{1 } \) x \( { D}_{1 } \) = \( { M}_{2 } \) x \( { D}_{2 } \) where, M = No. of Men, D = No. of Days, ⇒ Putting the values in the formula, ⇒ X x 15 = (X x 3) + (X + 10) x 8 ⇒ 15X = 3X + 8X + 80 ⇒ 15X - 11X = 80 ⇒ 4X = 80, ⇒ X = 20. |