P and Q together can do a piece of work in 60 days. Q and R together can do it in 120 days. P and R together can do it in 90 days. In what time can Q alone do the same work?
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → 144 days
Step 1: Let the work rates
Let total work = 1 unit.
- P + Q together can do the work in 60 days → work rate:
$P + Q = \frac{1}{60}$
- Q + R together can do the work in 120 days → work rate:
$Q + R = \frac{1}{120}$
- P + R together can do the work in 90 days → work rate:
$P + R = \frac{1}{90}$
Step 2: Add all three equations
$(P + Q) + (Q + R) + (P + R) = \frac{1}{60} + \frac{1}{120} + \frac{1}{90}$
$2P + 2Q + 2R = ?$
Compute RHS (LCM = 360):
$\frac{1}{60} = \frac{6}{360}, \quad \frac{1}{120} = \frac{3}{360}, \quad \frac{1}{90} = \frac{4}{360}$
$\text{Sum} = \frac{6 + 3 + 4}{360} = \frac{13}{360}$
$(P + Q + R) = \frac{13}{360} \quad \Rightarrow \quad P + Q + R = \frac{13}{720}$
Step 3: Find Q alone
$Q = (P + Q + R) - (P + R) = \frac{13}{720} - \frac{1}{90}$
$\frac{1}{90} = \frac{8}{720} \quad \Rightarrow \quad Q = \frac{13}{720} - \frac{8}{720} = \frac{5}{720}$
- Work rate of Q = 5/720 per day → time taken = $\frac{1}{5/720} = \frac{720}{5} = 144$