40 men can complete a work in 30 days. They start work together and after every 10 days five men left the work. In how much time work will be complete. |
40 36 39 25 |
36 |
40 men can do the work in 30 days let efficiency of 1 men = 1 Total work = Efficiency × Number of days Total work = 40 × 30 = 1200 According to the question, after every 10th day, 5 men leave. That means when the work began there were 40 men. After 10 days of work, there were 35 men, after another 10 days there were 30 men and so on. 40 men work in 10 days = 400 men days 35 men work in 10 days = 350 men days 30 men work in 10 days = 300 men days Total work till now = 1050 remaining work = 1200 - 1050 = 150 & now men left are 25 men so time taken = \(\frac{150}{25}\) = 6 days Total days taken to finish the work = 30 + 6 = 36 days |