Arrange the steps of planning process in correct sequence.
A. Evaluating alternative courses
B. Implementing the plan
C. Identifying alternate courses of action
D. Follow up action
E. Selecting the alternative
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → C, A, E, B, D
Step 1 — (C) Identifying alternate courses of action — Once objectives are set, the manager lists all the different ways in which the work can be done.
Step 2 — (A) Evaluating alternative courses — Next, the good points and bad points (pros and cons) of each way are weighed against the objective.
Step 3 — (E) Selecting the alternative — Now the best plan is chosen. This is the real point of decision making.
Step 4 — (B) Implementing the plan — The chosen plan is put into action. Other functions like organising also come in here.
Step 5 — (D) Follow up action — Last, the manager watches (monitors) the plan to see that the work goes as per schedule and the objectives are achieved.
NCERT (2026-27 Edition): “(iii) Identifying alternative courses of action: Once objectives are set, assumptions are made. Then the next step would be to act upon them. There may be many ways to act and achieve objectives. All the alternative courses of action should be identified. …” “(iv) Evaluating alternative courses: The next step is to weigh the pros and cons of each alternative. Each course will have many variables which have to be weighed against each other. The positive and negative aspects of each proposal need to be evaluated in the light of the objective to be achieved. …” “(v) Selecting an alternative: This is the real point of decision making. The best plan has to be adopted and implemented. …” “(vi) Implementing the plan: This is the step where other managerial functions also come into the picture. The step is concerned with putting the plan into action, i.e., doing what is required. …” “(vii) Follow-up action: To see whether plans are being implemented and activities are performed according to schedule is also part of the planning process. Monitoring the plans is equally important to ensure that objectives are achieved.” |