Aadish can complete a work in 14 days. If he worked for 8 days, then what fraction of the work would be left? |
$\frac{2}{7}$ $\frac{3}{7}$ $\frac{4}{7}$ $\frac{1}{7}$ |
$\frac{3}{7}$ |
Aadish = 14 days, Take Aadish's efficiency as 1. Therefore, Total work = 1 x 14 = 14 units, ⇒ He worked for 8 days = 1 x 8 = 8 units, ⇒ Fraction of work left = \(\frac{14-8}{14}\) = \(\frac{6}{14}\) = \(\frac{3}{7}\) |