K1 can do a piece of work alone in 4 days, K2 can do the same work alone in 8 days, while K3 can do it alone in 32 days. They work together and complete the work, and receive a total of ₹3,900 as payment for doing the work. What is the share of the person who received the maximum amount? |
₹1,200 ₹2,400 ₹2,000 ₹1,600 |
₹2,400 |
K1 = 4 days, K2 = 8 days, K3 = 32 days, ⇒ Total wages for working together = Rs. 3900 ⇒ (8 + 4 + 1)x = 3900 ⇒ 13x = 3900, ⇒ x = Rs. 300, ⇒ As K1 has highest efficiency, so he does the most work, therefore his share is = 8 x 300 = Rs. 2400. |