Which of the following is NOT related to the types of plan?
Answer & explanation
Correct answer: option 4
The correct answer is Option (4) → Monitoring
Option (1) Policy — A type of plan (Incorrect). A policy is a general statement that guides thinking and decisions, such as the admission policy of a school.
Option (2) Budget — A type of plan (Incorrect). A budget is a plan that shows expected results in numbers, such as a sales budget.
Option (3) Strategy — A type of plan (Incorrect). A strategy is a broad plan made by top management. It decides the long-term direction and the use of resources.
Option (4) Monitoring — Not a type of plan (Correct). Monitoring is not a plan. The types of plans are objectives, strategy, policy, procedure, method, rule, programme and budget. Monitoring is not one of them. It is part of the last step of the planning process, called follow-up action. Here the manager checks whether the plans are being carried out as decided.
NCERT (2026-27 Edition): “Follow-up action: To see whether plans are being implemented and activities are performed according to schedule is also part of the planning process. Monitoring the plans is equally important to ensure that objectives are achieved.” “Types of Plans … Based on what the plans seek to achieve, plans can be classified as Objectives, Strategy, Policy, Procedure, Method, Rule, Programme, Budget.” |