P alone can complete a work in 15 days and Q alone can complete the same work in 12 days. They start the work together but after 3 days P leaves the work. How much time will Q take to finish the remaining work? |
7.2 days 7.8 days 8.5 days 6.6 days |
6.6 days |
efficiency ∝ $\frac{1}{time}$ P : Q time 15 : 12 efficiency 4 : 5 ⇒ total = 9 Total work = LCM of 12, 15 = 60 Work done by P and Q together in 3 days = efficiency of P & Q x 3 = 9 x 3 = 27 Work left = 60 - 27 = 33 Time taken by Q alone to complete the remaining work = $\frac{remaining\;work}{efficiency}$ = $\frac{33}{5}$ = 6.6 days |