Target Exam

CUET

Subject

Business Studies

Chapter

Principles of Management

Question:

One of the technique of scientific management differentiates between efficient and inefficient workers. It advocates that efficient workers should be paid higher wages than inefficient workers.

Identify the technique.

Options:

Differential Piece Wage System

Fatigue Study

Method Study

Time Study

Correct Answer:

Differential Piece Wage System

Explanation:

The correct answer is Option (1) → Differential Piece Wage System.

Differential Piece Wage System differentiates between efficient and inefficient workers. It advocates that efficient workers should be paid higher wages than inefficient workers.

Differential piece wage system - Taylor was a strong advocate of piece wage system. He wanted to differentiate between efficient and inefficient workers. The standard time and other parameters should be determined on the basis of the work-study. The workers can then be classified as efficient or inefficient on the basis of these standards. He wanted to reward efficient workers. So he introduced different rate of wage payment for those who performed above standard and for those who performed below standard.

 

OTHER OPTIONS

  • Time study determines the standard time taken to perform a well-defined job. Time measuring devices are used for each element of task. The standard time is fixed for the whole of the task by taking several readings. The method of time study will depend upon the volume and frequency of the task, the cycle time of the operation and time measurement costs. The objective of the time study is to determine the number of workers to be employed; frame suitable incentive schemes and determine labour costs.
  • Method Study- The objective of method study is to find out one best way of doing the job. There are various methods of doing the job. To determine the best way there are several parameters. Right from procurement of raw materials till the final product is delivered to the customer every activity is part of method study. Taylor devised the concept of assembly line by using method study.
  • Fatigue Study- A person is bound to feel tired physically and mentally if she/he does not rest while working. The rest intervals will help one to regain stamina and work again with the same capacity. This will result in increased productivity. Fatigue study seeks to determine the amount and frequency of rest intervals in completing a task. For example, normally in a plant, work takes place in three shifts of eight hours each. Even in a single shift, a worker has to be given some rest interval to take her/his lunch, etc. If the work involves heavy manual labour then small pauses have to be frequently given to the worker so that she/he can recharge her/his energy level for optimum contribution. There can be many causes for fatigue like long working hours, doing unsuitable work, having uncordial relations with the boss or bad working conditions etc. Such hindrances to good performance should be removed.