X, Y and Z together can complete a work in 6 days. X as well as Y alone can do the same work in 16 days. In how many days can Z alone complete the same work? |
12 16 24 36 |
24 |
X as well as Y alone can do a work in 16 days. X one day work = 1/16 Y one day work = 1/16 X, Y, Z can do it together in 6 days Assume Z takes "z" days to complete the work alone. Z one day work = 1/z One day work of X, Y and Z working together = 1/6 ⇒1/16 + 1/16 + 1/z = 1/6 1/z = 1/6 - 2/16 = (4-3 )/24 z = 24 The correct answer is Option (3) → 24 |