Identify the correct sequence of controlling process
(A) Identifying the deviations from the standards established.
(B) Measuring the performance of the employees.
(C) If there are deviations, corrective action is called for.
(D) Establishment of standards or targets against which the actual performance is measured.
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → (D), (B), (A), (C)
The controlling process has this order:
(D) Establishment of standards or targets — first, standards are set. Actual performance will be measured against them.
(B) Measuring the performance of the employees — next, the actual work done is measured.
(A) Identifying the deviations from the standards established — then the actual performance is compared with the standards. This shows the deviations (gaps), which are then analysed.
(C) If there are deviations, corrective action is called for — last, steps are taken to remove the gaps.
NCERT (2026-27 Edition): “Controlling Process Controlling is a systematic process involving the following steps. |