Based on the following case-study, answer the question.
Mr. Arfaaz had been heading the production department of writewell products Ltd., a firm manufacturing stationery items. The firm secured an export order that had to be completed on a priority basis and production targets were defined for all the employees. One of the workers, Mr. Bhanu Prasad, fell short of his daily production target by 10 units for two days consecutively. Mr. Arfaaz approached Ms Vasundhara, the CEO of the company to file a complaint against Mr. Bhanu Prasad and requested her to terminate his services.
Select the step of the function of management that help Mr. Arfaaz in finding that Mr. Bhanu Prasad fell short of his daily production target by 10 units for two days consecutively.
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Comparing Actual Performance with Standards
Option (1) Setting Standards — Incorrect. This step fixed the daily production targets. It does not show any shortfall.
Option (2) Comparing Actual Performance with Standards — Correct. The daily production target was the standard. Mr. Bhanu Prasad’s actual output was put next to this target. This showed that he fell short by 10 units. Comparing actual performance with the standard reveals the deviation. For example, units produced by a worker are checked against the standard output.
Option (3) Analysing Deviations — Incorrect. This step comes after the gap is found. It looks for the size and the cause of the gap.
Option (4) Taking Corrective Action — Incorrect. This is the last step. It is the action taken to remove the gap. Finding the gap comes before it.
NCERT (2026-27 Edition): “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. Comparison becomes easier when standards are set in quantitative terms. For instance, performance of a worker in terms of units produced in a week can be easily measured against the standard output for the week.” |