Bira Machines Limited is engaged in manufacturing of machine components. The company has planned to venture into automobile parts as well for which, it started doing the market research. The target production for machine parts is 500 units per day per worker. The company had been successfully attaining this target until four months ago. The company follows a practice where only significant deviations from a budget or plan are brought to the attention of management. Over the last four months, it has been observed that daily production varies between 450-460 units per day per worker. Management called the supervisor and asked him to find out the reasons for low productivity. CCTV cameras were installed to keep a check on employees. It was found that some of the workers used to spend more time for lunch than allotted. The report for the same was prepared and submitted by the supervisor to the management.
“Over the last four months, it has been observed that daily production varies between 450-460 units per day per worker.”
Which step of the controlling process has been carried out by the company here?
Answer & explanation
Correct answer: option 2
The correct answer is Option (2) → Measuring Actual Performance
Option (1) Setting performance standards — Incorrect. Setting performance standards is the first step: fixing the criteria against which actual performance will be measured. Here the standard, 500 units per day per worker, had been set long before.
Option (2) Measuring Actual Performance — Correct. Observing that each worker now makes 450-460 units a day is recording actual performance, in the same units as the standard.
Option (3) Analysing Deviations — Incorrect. Analysing deviations means finding their causes. That comes later, when the supervisor looks into the reasons.
Option (4) Taking corrective action — Incorrect. Corrective action is the final step, taken after the causes are known. The given line only records output; no action is taken yet.
NCERT (2026-27 Edition): “Step 2: Measurement of Actual Performance: Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. There are several techniques for measurement of performance. These include personal observation, sample checking, performance reports, etc. As far as possible, performance should be measured in the same units in which standards are set as this would make their comparison easier.” |