Mr. Armaan is appointed as Quality control manager in a factory. The list of steps to monitor the performance is shared with him. Mr Armaan is asked to put the following steps in correct order.
(A) Employees must be trained to meet the targets in future, so that deviations do not reoccur
(B) Comparing the criteria set with the report of personal observation
(C) Setting the criteria against which actual performance would be measured
(D) Keeping in mind the key result area, the deviations which go beyond the permissible limit is to brought to the notice
(E) Personally observe the work done by workers
Choose the correct answer from the options given below:
Answer & explanation
Correct answer: option 3
The correct answer is Option (3) → (C), (E), (B), (D), (A)
(C) Setting the criteria against which actual performance would be measured — first. This is setting performance standards. Standards are the criteria against which actual performance would be measured. Nothing can be checked until the standard is fixed.
(E) Personally observe the work done by workers — second. This is measurement of actual performance. Personal observation is one of the ways of measuring performance.
(B) Comparing the criteria set with the report of personal observation — third. This is comparing actual performance with standards. It shows the gap (deviation) between what was planned and what was done. It needs both the standard (C) and the measurement (E).
(D) Keeping in mind the key result area, the deviations which go beyond the permissible limit is to brought to the notice — fourth. This is analysing deviations. The manager uses critical point control (focus on key result areas) and management by exception (report only deviations beyond the permissible limit).
(A) Employees must be trained to meet the targets in future, so that deviations do not reoccur — last. This is taking corrective action. Training of employees is an example of corrective action, so that deviations do not occur again.
NCERT (2026-27 Edition): “Step 1: Setting Performance Standards: … The first step in the controlling process is setting up of performance standards. Standards are the criteria against which actual performance would be measured. Thus, standards serve as benchmarks towards which an organisation strives to work.” “Step 2: Measurement of Actual Performance: … Once performance standards are set, the next step is measurement of actual performance. Performance should be measured in an objective and reliable manner. There are several techniques for measurement of performance. These include personal observation, sample checking, performance reports, etc. …” “Step 3: Comparing Actual Performance with Standards: … This step involves comparison of actual performance with the standard. Such comparison will reveal the deviation between actual and desired results. …” “Step 4: Analysing Deviations: Some deviation in performance can be expected in all activities. It is, therefore, important to determine the acceptable range of deviations. Also, deviations in key areas of business need to be attended more urgently as compared to deviations in certain insignificant areas. Critical point” “…control and management by exception should be used by a manager in this regard.” “Critical Point Control: It is neither economical nor easy to keep a check on each and every activity in an organisation. Control should, therefore, focus on key result areas (KRAs) which are critical to the success of an organisation. …” “Management by Exception: Management by exception, which is often referred to as control by exception, is an important principle of management control based on the belief that an attempt to control everything results in controlling nothing. Thus, only significant deviations which go beyond the permissible limit should be brought to the notice of management. …” “Step 5: Taking Corrective Action: The final step in the controlling process is taking corrective action. No corrective action is required when the deviations are within acceptable limits. …” “Corrective action might involve training of employees if the production target could not be met. …” |