Bira Machines Limited is engaged in manufacturing of machine components. The company has planned to venture into automobile parts as well for which, it started doing the market research. The target production for machine parts is 500 units per day per worker. The company had been successfully attaining this target until four months ago. The company follows a practice where only significant deviations from a budget or plan are brought to the attention of management. Over the last four months, it has been observed that daily production varies between 450-460 units per day per worker. Management called the supervisor and asked him to find out the reasons for low productivity. CCTV cameras were installed to keep a check on employees. It was found that some of the workers used to spend more time for lunch than allotted. The report for the same was prepared and submitted by the supervisor to the management.
“Management called the supervisor and asked him to find out the reasons for low productivity.”
The supervisor’s work forms part of which step of the controlling process?
Answer & explanation
Correct answer: option 1
The correct answer is Option (1) → Analysing deviations
Option (1) Analysing deviations — Correct. The deviation is already known: output fell from 500 to 450-460 units. Finding out why it happened is analysing the deviation for its causes. Here the cause found was workers taking longer lunch breaks.
Option (2) Measurement of actual performance — Incorrect. Measurement was done earlier, when the daily output of 450-460 units was observed.
Option (3) Taking corrective action — Incorrect. Corrective action comes after the cause is known, for example fixing lunch timings. The supervisor only finds and reports the cause.
Option (4) Comparing actual performance with standards — Incorrect. Comparing the actual 450-460 units with the standard of 500 is what showed the deviation, before the supervisor was called.
NCERT (2026-27 Edition):
NCERT (2026-27 Edition): “… control and management by exception should be used by a manager in this regard.”
|