A, B and C can do piece of work in 30 days, 45 days and 90 days, respectively. A starts the work and he is assisted by B and C together on every third day. In how many days will the work be completed? |
23 24 30 $22\frac{1}{2}$ |
23 |
A = 30 days, B = 45 days, C = 90 days, ⇒ Since A is working daily and B & C assist him on every third day, the efficiencies will be as follows: 1st day (A) = 3 units 2nd day (A) = 3 units 3rd day (All) = 3 + 2 + 1 = 6 units Every 3 days work = 3 + 3 + 6 = 12 units. Hence, in 21 days, 84 units of work will be completed. and in 23 days. 90 units of work will be completed. Therefore, time taken to complete the total work will be 23 days. |