………….are relevant only for recurring activities.
Answer & explanation
Correct answer: option 2
The correct answer is option 2 i.e. Standing Plans.
A standing plan is used for activities that occur regularly over a period of time. It is designed to ensure that internal operations of an organisation run smoothly. Such a plan greatly enhances efficiency in routine decision-making. It is usually developed once but is modified from time to time to meet business needs as required. Standing plans include policies, procedures, methods and rules.