A and B can complete a work in 10 and 15 days respectively. A and B start working together and after 4 days, A left the work. Find in how many days work will be completed. |
6 8 9 5 |
9 |
Total work = Efficiency × Number of days Work done by ( A + B ) in 4 days = 5 x 4 = 20 Remaining work = 30 - 20 = 10 Time taken by B to complete the remaining work = \(\frac{10}{2}\) = 5 Total time taken in doing whole work = 4 + 5 = 9 days |